Installation — Machine NX-200
Warning: Qualified personnel only
Installation and connection of the NX-200 must only be performed by an authorised electrician and machine technician. Unauthorised installation voids the warranty and may pose a serious safety risk.
Prerequisites
Verify the following before installation:
- [ ] 400 V / 3-phase / 50 Hz socket (CEE 32A) within 3 metres
- [ ] Compressed air (6 bar, min. 200 l/min) with 1/2" connection
- [ ] Floor space minimum 4 × 2 m (including operating area)
- [ ] Floor load capacity minimum 500 kg/m²
- [ ] Ambient temperature +5 °C to +40 °C
- [ ] Relative humidity below 80% (non-condensing)
Installation Procedure
1. Unpacking
- Remove packaging carefully — avoid damaging the cabinets.
- Check the machine condition against the delivery note.
- Report transport damage within 24 hours to the carrier.
2. Positioning
- Place the machine on the prepared surface.
- Retract the four transport wheels and level the machine with the adjusting feet.
- Check horizontal alignment with a spirit level — maximum deviation 2 mm/m.
- Tighten the adjusting feet lock nuts.
3. Electrical Connection
- Ensure power supply is disconnected (LOTO procedure — see Safety section).
- Connect the CEE 32A plug to the machine's connection cabinet.
- Check phase sequence — correct direction of rotation of the conveyor belt is indicated by an arrow on the cabinet.
- Apply power and confirm green indicator on HMI.
4. Compressed Air Connection
- Connect the 1/2" compressed air fitting to the machine inlet (blue label, left side panel).
- Open the shut-off valve slowly.
- Check the pressure gauge on the machine: operating pressure should read 5.5–6.5 bar.
5. Commissioning
- Switch on the machine via the HMI panel (green START button).
- Run the machine idle for 5 minutes and check for abnormal noises.
- Run a test with packaging film without product — check seal quality.
- Record commissioning date and technician initials in the service log.